Del Title Description
D1.1 Report on best practices Report comparing current approaches to Circular Economy in the Food Industry identifying best practice approaches
D1.2 Report about performance evaluation methodologies Methodological report about performance evaluation methodologies for agri-food supply chains (social, environmental and economic).
D1.3 Case studies Case Studies about the evaluation of the implementation of Circular Economy practices in selected agri-food supply chains
D2.1 Report on current drivers and barriers to CE Report about current drivers and barriers to Circular Economy practices implementations in the different surveyed geographical contexts.
D2.2 Report on current policies Report reviewing current policies (and potential recommendations) for Circular Economy practices implementations in agri-food systems in the different surveyed geographical contexts.
D3.1 Initial Project Meeting Kick-Off Project Meeting
D3.2 Mid-Term Meeting Mid-Term Meeting
D4.1 Dissemination Plan Dissemination Plan
D4.2 Project website Launch and maintenance of the project website
D5.1 Follow-up plan Final follow-up plan
D6.1 H – Requirement No. 2 Details on the procedures and criteria that will be used to identify/recruit research participants must be submitted as a deliverable, before the commencement of the relevant research.
D6.2 POPD – Requirement No. 3 A description of the anonymysation/pseudonymisation techniques that will be implemented must be submitted as a deliverable.
D6.3 H – Requirement No. 4 Detailed information on the informed consent procedures that will be implemented for the participation of humans and in regard to data processing must be submitted as a deliverable, before the commencement of the relevant research.

N. Title WP Lead Due Date Means of Verification
M1 Engagement Methodology Piloting 2 SEERC 8 The stakeholders’ engagement methodology will be consolidated through some piloting exercises.
M2 Pilot evaluation methodology and data collection protocol 1 UPN 12 The specification of the evaluation framework will be circulated through project and stakeholders’ network, along with the related data collection protocol; validation will be required; feedback will be incorporated in the final version
M3 Secondments progress 3 USFD 18 Check about the correct performance of secondments against schedule
M4 Academic papers progress 4 USFD 26 Draft papers are submitted for internal review by the supervisory board.
M5 Policy briefs progress 4 USFD 26 Draft briefs should be submitted for internal review by the supervisory board
M6 Follow-up progress 5 USFD 32 Draft follow-up plan will be submitted for internal review by the supervisory board.